Add holidays & vacations
There are two ways to create Team Calendar events:
Resources Tab > Team Calendar - Must be an adminResource 360 > Calendar - Individuals create their own events
Resources Tab > Team Calendar
Use the Team Calendar to create events that account for company-wide holidays, individual resource vacations, business travel, etc. Team Calendar events are factored into resource forecasting calculations. A few caveats:
- All users can view the Team Calendar but only admins can add or edit events
- Team Calendar events are independent from Basecamp events and do not get exported or synced
Go to Resources Tab > Team Calendar and click on any day to create or edit an event.
Resource 360 > Calendar
Go to your Resource 360 > Calendar page and click on any day to create or edit an event