Resource collision alerts

Resource Collisions

Resource collisions occur when a resource exceeds 100% for particular day (each day equals one collision). The red collision notification is displayed at the top of any app page and is only visible when collisions exist.

The example below demonstrates a new assignment that triggers a new resource collision.* Moments after the new assignment is created the system recognizes the resource exceeds 100% capacity for one or more days. Clicking the collision notification icon opens the collision summary page. The collision details page allows users to eliminate ‘double-parked’ situation by swapping resources.

*A more typical example is when a new project is created from template or imported from a 3rd party app.