Schedule Audit column group
The Schedule Audit column group, available on the Projects Tab , includes the following columns:
- Accuracy (%) - Accuracy of original project duration (measured in workdays)
- Changes - Counts the number of date changes that extended project duration
- Planned - Original project due date
- Drift (days) - Difference in workdays between planned and projected due date
- Projected - Projected product due date
Note: Schedule Audit and Schedule Audit column group are only available to Pro subscription plans.